Highway 210 reconstruction remains in the 2026 railyard phase
MnDOT's two-year Washington Street/Highway 210 reconstruction is continuing through Brainerd, with work spanning from Baxter Drive to Pine Shores Road.
The $46 million project includes roadway reconstruction or resurfacing, curbs, storm sewer, signals, utility work, pedestrian improvements, trail connections and changes at Highway 25/Mill Avenue.
The 2026 schedule lists the east segment for spring through fall, the mall segment from May 18 to mid-September and the railyard segment from August 10 through fall. Downtown, bridge and west-segment work is scheduled for 2027.
Baxter
Lower public-transit fares are now in effect for trips starting in Baxter
Brainerd & Crow Wing Public Transit lowered fares for trips originating in Baxter effective September 21.
Advance reservations now cost $3 and same-day reservations cost $5, matching the fare structure for trips originating in Brainerd.
Brainerd
Preliminary 2027 city levy set at maximum 9.9%
Brainerd Dispatch reporting says the City Council set the preliminary 2027 levy at a maximum increase of 9.9% during its September 21 meeting.
The report says council members expect the final number to be lower when the levy is adopted at the end of the year. A preliminary levy can be reduced before final adoption.
Brainerd
Public Utilities Commission meets Tuesday
The Brainerd Public Utilities Commission is scheduled to meet Tuesday, September 29 at 9 a.m.